AZ Delta - remodeling and renovation OK campus Brugsesteenweg

At AZ Delta, Brugsesteenweg campus in Roeselare, the existing operating theater (Block C) is being remodeled and expanded on level 3 (with associated new technical spaces on level+2, and remodeling of existing technical space on level +4)

AUDITOR

AZ DELTA

ARCHITECT

M4 architects

LOCATION

Roeselare

OPPORTUNITY

4.500m2

BUDGET

approx. 14,000,000 EUR (excl. VAT) total construction budget

PERIOD

study 2021-2023

works 2024-2026

Services
No items found.
Sectors
No items found.
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg

AZ Delta - remodeling and renovation OK campus Brugsesteenweg

At AZ Delta, Brugsesteenweg campus in Roeselare, the existing operating theater (Block C) is being remodeled and expanded on Level 3 (with associated new technical spaces on Level +2, and remodeling of existing technical space on Level +4).

In a preliminary file, "a level 0 area (kitchen and pharmacy) is being remodeled and preparations are being made to eliminate the current technical space on the roof of the C block, without impeding activity within the existing hospital.

The expansion will accommodate up to 8 OP rooms. The existing OP quarter will be converted to a pre and post operative admission area.

Ingenium designs the complete technical systems for both new construction and renovation, with coupling to the existing central systems. Great attention is paid to the ventilation of the OP rooms from the technical space below, in order to guarantee a laminar flow and thus perfect air quality in each room. Naturally, great attention is also paid to (electrical) patient safety.

Up to PV panels are provided on the roof of the new building volume.

Ingenium also prepares the file for the medical shuttles.

ref. 21077.002

AZ Delta - remodeling and renovation OK campus Brugsesteenweg

AZ Delta - remodeling and renovation OK campus Brugsesteenweg

At AZ Delta, Brugsesteenweg campus in Roeselare, the existing operating theater (Block C) is being remodeled and expanded on level 3 (with associated new technical spaces on level+2, and remodeling of existing technical space on level +4)

AUDITOR

AZ DELTA

ARCHITECT

M4 architects

LOCATION

Roeselare

OPPORTUNITY

4.500m2

BUDGET

approx. 14,000,000 EUR (excl. VAT) total construction budget

PERIOD

study 2021-2023

works 2024-2026

Services
No items found.
Sectors
No items found.
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg

AZ Delta - remodeling and renovation OK campus Brugsesteenweg

At AZ Delta, Brugsesteenweg campus in Roeselare, the existing operating theater (Block C) is being remodeled and expanded on Level 3 (with associated new technical spaces on Level +2, and remodeling of existing technical space on Level +4).

In a preliminary file, "a level 0 area (kitchen and pharmacy) is being remodeled and preparations are being made to eliminate the current technical space on the roof of the C block, without impeding activity within the existing hospital.

The expansion will accommodate up to 8 OP rooms. The existing OP quarter will be converted to a pre and post operative admission area.

Ingenium designs the complete technical systems for both new construction and renovation, with coupling to the existing central systems. Great attention is paid to the ventilation of the OP rooms from the technical space below, in order to guarantee a laminar flow and thus perfect air quality in each room. Naturally, great attention is also paid to (electrical) patient safety.

Up to PV panels are provided on the roof of the new building volume.

Ingenium also prepares the file for the medical shuttles.

ref. 21077.002

AZ Delta - remodeling and renovation OK campus Brugsesteenweg
Oops! Something went wrong while submitting the form.

AZ Delta - remodeling and renovation OK campus Brugsesteenweg

At AZ Delta, Brugsesteenweg campus in Roeselare, the existing operating theater (Block C) is being remodeled and expanded on level 3 (with associated new technical spaces on level+2, and remodeling of existing technical space on level +4)

AUDITOR

AZ DELTA

ARCHITECT

M4 architects

LOCATION

Roeselare

OPPORTUNITY

4.500m2

BUDGET

approx. 14,000,000 EUR (excl. VAT) total construction budget

PERIOD

study 2021-2023

works 2024-2026

Services
No items found.
Sectors
No items found.
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg
AZ Delta - remodeling and renovation OK campus Brugsesteenweg

AZ Delta - remodeling and renovation OK campus Brugsesteenweg

At AZ Delta, Brugsesteenweg campus in Roeselare, the existing operating theater (Block C) is being remodeled and expanded on Level 3 (with associated new technical spaces on Level +2, and remodeling of existing technical space on Level +4).

In a preliminary file, "a level 0 area (kitchen and pharmacy) is being remodeled and preparations are being made to eliminate the current technical space on the roof of the C block, without impeding activity within the existing hospital.

The expansion will accommodate up to 8 OP rooms. The existing OP quarter will be converted to a pre and post operative admission area.

Ingenium designs the complete technical systems for both new construction and renovation, with coupling to the existing central systems. Great attention is paid to the ventilation of the OP rooms from the technical space below, in order to guarantee a laminar flow and thus perfect air quality in each room. Naturally, great attention is also paid to (electrical) patient safety.

Up to PV panels are provided on the roof of the new building volume.

Ingenium also prepares the file for the medical shuttles.

ref. 21077.002

AZ Delta - remodeling and renovation OK campus Brugsesteenweg

Related projects

No items found.

Also bitten by
smart technology?

Come push boundaries with us and help make a difference in our industry-leading projects.

No items found.