25043.001

Improving the user experience at Credendo Bank’s headquarters in Brussels

Regulatory Audit and Optimization Follow-Up

Location

3 Rue Montoyer, Brussels-Capital Region, 1000

Client

Credendo

Budget studies

€25,000.00 (excl. tax)

Timing studies

Start: April 2025

End of February 2026

Services
No items found.

Regulatory Audit and Optimization Support

‍System audit based on the inventory of technical systems covered by the maintenance contract.

Ingenium recommends performing a quick scan of the system using the building management system (BMS) as a tool. The goal is to determine whether the system is functioning independently and optimally. A list of malfunctions and opportunities for optimization will be compiled. If available, we will use the functional description that Honeywell used as the basis for programming.

Ingenium is drawing up a step-by-step action plan:

1) Requesting all relevant documents prior to the visit,

2) Scheduling the on-site visit and requesting remote access to the BMS

3) Conformity check/functional description

4) preparing a report that describes the situation and provides a clear overview of the installation

5) An on-site brainstorming session to discuss installation issues and potential improvements.

Seasonal audit optimization (average of 1 day per month)

- Remote monitoring of the BMS and reporting (once a month)

- Quarterly on-site visit with the maintenance company SPIE

Complete satisfaction among users, the technical team, and Credendo’s management after six months of collaboration.

Also bitten by
smart technology?

Come push boundaries with us and help make a difference in our industry-leading projects.

Improving the user experience at Credendo Bank’s headquarters in Brussels

Regulatory Audit and Optimization Support

‍System audit based on the inventory of technical systems covered by the maintenance contract.

Ingenium recommends performing a quick scan of the system using the building management system (BMS) as a tool. The goal is to determine whether the system is functioning independently and optimally. A list of malfunctions and opportunities for optimization will be compiled. If available, we will use the functional description that Honeywell used as the basis for programming.

Ingenium is drawing up a step-by-step action plan:

1) Requesting all relevant documents prior to the visit,

2) Scheduling the on-site visit and requesting remote access to the BMS

3) Conformity check/functional description

4) preparing a report that describes the situation and provides a clear overview of the installation

5) An on-site brainstorming session to discuss installation issues and potential improvements.

Seasonal audit optimization (average of 1 day per month)

- Remote monitoring of the BMS and reporting (once a month)

- Quarterly on-site visit with the maintenance company SPIE

Complete satisfaction among users, the technical team, and Credendo’s management after six months of collaboration.

Improving the user experience at Credendo Bank’s headquarters in Brussels

Regulatory Audit and Optimization Follow-Up

Location

3 Rue Montoyer, Brussels-Capital Region, 1000

Client

Credendo

Budget studies

€25,000.00 (excl. tax)

Timing studies

Start: April 2025

End of February 2026

Services
No items found.
Sectors

Improving the user experience at Credendo Bank’s headquarters in Brussels

Regulatory Audit and Optimization Support

‍System audit based on the inventory of technical systems covered by the maintenance contract.

Ingenium recommends performing a quick scan of the system using the building management system (BMS) as a tool. The goal is to determine whether the system is functioning independently and optimally. A list of malfunctions and opportunities for optimization will be compiled. If available, we will use the functional description that Honeywell used as the basis for programming.

Ingenium is drawing up a step-by-step action plan:

1) Requesting all relevant documents prior to the visit,

2) Scheduling the on-site visit and requesting remote access to the BMS

3) Conformity check/functional description

4) preparing a report that describes the situation and provides a clear overview of the installation

5) An on-site brainstorming session to discuss installation issues and potential improvements.

Seasonal audit optimization (average of 1 day per month)

- Remote monitoring of the BMS and reporting (once a month)

- Quarterly on-site visit with the maintenance company SPIE

Complete satisfaction among users, the technical team, and Credendo’s management after six months of collaboration.

Oops! Something went wrong while submitting the form.