Electricity master plan European Parliament
One of the most complex master plan studies.
Client
European Parliament
Budget techniques
3,940,764.17 € (excluding VAT)
Surface
500.000 m²
Period
2010 - present
Electricity master plan European Parliament
One of the most complex master plan studies.
This is a building of approximately 300,000 m2 whose all-electric heart is being renovated and optimized in full operation.
Content:
- Replacement of 4 high voltage cabins
- Replacement of 21 1MVA transformers.
- Installation of 2 additional of 1MVA
- Adding 2 MVA of diesel power on top of the existing 3MVA of diesel power
- Synchronization of the diesel with each other (old new)
- Synchronization of the diesels at high voltage (i.e. it is possible to go into island with the emergency groups at reduced power)
- SCADA package that visualizes and can automatically control diesels and high voltage
- Integration of electrical building management system
- Replacement of 1 MVA of UPS power
- Bringing the installation into compliance with the new AREI 2020
Extremely special is not only the size, but also that the building should not be affected. It is not obvious to replace a high-voltage board with 23 cells without the users noticing anything. The totality of the project, with all the above works completed, is realized in the summer of 2023.