Poultry slaughterhouse Cooreman is doubling its production, exceeding the limit of 0.1 PJ of primary annual energy consumption and thus becoming an energy-intensive company. The environmental permit requires an energy study of the expansion and, because the 0.1 PJ limit is exceeded, an energy plan of the entire plant.

COOREMAN - Energy study and energy plan.

COOREMAN - Energy study and energy plan.

Client

Pluimveeslachterij Cooreman nv

Location

Dendermonde

Period Study

02/2020-08/2021

COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.

COOREMAN - Energy study and energy plan.

Poultry slaughterhouse Cooreman is doubling its production, exceeding the limit of 0.1 PJ of primary annual energy consumption and thus becoming an energy-intensive company. The environmental permit requires an energy study of the expansion and, because the 0.1 PJ limit is exceeded, an energy plan of the entire plant.

COOREMAN - Energy study and energy plan.
Oops! Something went wrong while submitting the form.
19099.003

COOREMAN - Energy study and energy plan.

Client

Pluimveeslachterij Cooreman nv

Location

Dendermonde

Period Study

02/2020-08/2021

COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.
COOREMAN - Energy study and energy plan.

COOREMAN - Energy study and energy plan.

Poultry slaughterhouse Cooreman is doubling its production, exceeding the limit of 0.1 PJ of primary annual energy consumption and thus becoming an energy-intensive company. The environmental permit requires an energy study of the expansion and, because the 0.1 PJ limit is exceeded, an energy plan of the entire plant.

COOREMAN - Energy study and energy plan.

Related projects

High Voltage 150 kV GIS + 22 kV MV

High Voltage 150 kV GIS + 22 kV MV
In the spotlight

High voltage 2x 150 kV/13 kV - AIS + 2x AIS 380 kV/150 kV

High voltage 2x 150 kV/13 kV - AIS + 2x AIS 380 kV/150 kV
In the spotlight

High-voltage preliminary design 150 kVA / 36 kV

High-voltage  preliminary design 150 kVA / 36 kV
In the spotlight

Preliminary design for a 36 kV high-voltage connection

Preliminary design for a 36 kV high-voltage connection
In the spotlight

36 kV high-voltage substation, 2 × 40 MVA

36 kV high-voltage substation, 2 × 40 MVA
In the spotlight

High-voltage feasibility study for 150 kV (Hitachi + Siemens)

High-voltage feasibility study for 150 kV (Hitachi + Siemens)
In the spotlight

High-voltage preliminary design for a 36 kV connection and pre-design layout

High-voltage preliminary design for a 36 kV connection and pre-design layout
In the spotlight

Preliminary design for a 36 kV high-voltage substation

Preliminary design for a 36 kV high-voltage substation
In the spotlight

Van der Vlist Zeebrugge

Van der Vlist Zeebrugge
In the spotlight

ECS/ 2XL High-rise 2

ECS/ 2XL High-rise 2
In the spotlight

Zeebrugge Green Logistics

Zeebrugge Green Logistics
In the spotlight

DEMATRA HIGH-RISE WAREHOUSE

DEMATRA HIGH-RISE WAREHOUSE
In the spotlight

Also bitten by
smart technology?

Come push boundaries with us and help make a difference in our industry-leading projects.