17090.030

Preliminary design for a 36 kV high-voltage connection

Preliminary design for a 36 kV high-voltage connection

We assisted the customer in upgrading its power grid.

In the initial phase, we developed various concepts for grid reinforcement. Based on these, we requested grid studies from Fluvius and Elia. We examined the costs and technical feasibility of connecting to the Fluvius 36 kV grid or the Elia grid (36 kV or 150 kV). In doing so, we took into account connection costs charged by the grid operator, internal investment costs, and the impact on grid tariffs.

Now that this phase has been completed and the final grid studies have been requested, we have begun designing the final solution: a connection to Elia’s 36 kV grid.

Preliminary design for a 36 kV high-voltage connection

Related projects

High Voltage 150 kV GIS + 22 kV MV

High Voltage 150 kV GIS + 22 kV MV
In the spotlight

High voltage 2x 150 kV / 13 kV

High voltage 2x 150 kV / 13 kV
In the spotlight

Kevlinx Data Center

Kevlinx Data Center
In the spotlight

KevlinX Data Center 36 kV High-Voltage Substation 2x40 MVA

KevlinX Data Center 36 kV High-Voltage Substation 2x40 MVA
In the spotlight

High-voltage feasibility study for 150 kV (Hitachi + Siemens)

High-voltage feasibility study for 150 kV (Hitachi + Siemens)
In the spotlight

High-voltage preliminary design for a 36 kV connection and pre-design layout

High-voltage preliminary design for a 36 kV connection and pre-design layout
In the spotlight

Preliminary design for a 36 kV high-voltage substation

Preliminary design for a 36 kV high-voltage substation
In the spotlight

Van der Vlist Zeebrugge

Van der Vlist Zeebrugge
In the spotlight

ECS/ 2XL High-rise 2

ECS/ 2XL High-rise 2
In the spotlight

Zeebrugge Green Logistics

Zeebrugge Green Logistics
In the spotlight

DEMATRA HIGH-RISE WAREHOUSE

DEMATRA HIGH-RISE WAREHOUSE
In the spotlight

SEW Eurodrive - new warehouses and offices

SEW Eurodrive - new warehouses and offices
In the spotlight

Also bitten by
smart technology?

Come push boundaries with us and help make a difference in our industry-leading projects.

Preliminary design for a 36 kV high-voltage connection

Preliminary design for a 36 kV high-voltage connection

Preliminary design for a 36 kV high-voltage connection

Preliminary design for a 36 kV high-voltage connection

We assisted the customer in upgrading its power grid.

In the initial phase, we developed various concepts for grid reinforcement. Based on these, we requested grid studies from Fluvius and Elia. We examined the costs and technical feasibility of connecting to the Fluvius 36 kV grid or the Elia grid (36 kV or 150 kV). In doing so, we took into account connection costs charged by the grid operator, internal investment costs, and the impact on grid tariffs.

Now that this phase has been completed and the final grid studies have been requested, we have begun designing the final solution: a connection to Elia’s 36 kV grid.

Preliminary design for a 36 kV high-voltage connection
Preliminary design for a 36 kV high-voltage connection
Preliminary design for a 36 kV high-voltage connection
Preliminary design for a 36 kV high-voltage connection
Preliminary design for a 36 kV high-voltage connection
Preliminary design for a 36 kV high-voltage connection
Preliminary design for a 36 kV high-voltage connection

Preliminary design for a 36 kV high-voltage connection

Preliminary design for a 36 kV high-voltage connection
Oops! Something went wrong while submitting the form.