WZC Waegebrughe Kruisem

The non-profit organization Vijvens provided a new residential care center in Kruisem on the Marolle: Waegebrughe. Two buildings were constructed on the Waegebrughe campus: west and east of the church.

CLIENT

VZW the Vijvens

DESIGNER / ARCHITECT

sergison Baetes architects

LOCATION

Kruisem

BUDGET TECHNIQUES

approx. EUR 6,710,761

SURFACE

12.000m2

PERIOD STUDY

09/2013 - 12/2018

Period EXPERIENCE

05/2019 - 05/2022

WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem

WZC Waegebrughe Kruisem

The non-profit organization Vijvens provided a new residential care center in Kruisem on the Marolle: Waegebrughe. Two buildings were constructed on the Waegebrughe campus: west and east of the church.

A total of sixty rest home beds, twenty service flats, thirty assisted living or care flats, a day care center with fifteen places, nine short-stay rooms, two night care rooms and a center for the young demented, administrative and communal functions, large kitchen, technical and other facility rooms were created.

The large-scale project further includes a local service center with a social restaurant, a wellness for the elderly and a daycare center. This will provide a link to the neighborhood and associations.

Ingenium was responsible for the integral study of the techniques: sustainability studies, EPB reporting.

Study, design, competition file, follow-up of the works, commissioning on delivery, budget control, for these techniques: elevators, HVAC, kitchen, plumbing, elevators, electricity.

In terms of sustainability, the following interventions toward reusable energy are planned:

  • BEO field with passive cooling and heat pump for heating
  • Charging points for electric vehicles
  • For the residential units : storey stations with separate heat exchangers and energy metering
  • Cogeneration (does consume gas...)

Flexibility in design was provided in this way:

  • For each building, substations are provided for the techniques
  • A large number of technical ducts are provided per building so that extensions can easily be added
  • The distribution of techniques in the building is centralized by a horizontal distribution in the basement that then rises vertically to the floors through the ducts.

WZC Waegebrughe Kruisem

WZC Waegebrughe Kruisem

The non-profit organization Vijvens provided a new residential care center in Kruisem on the Marolle: Waegebrughe. Two buildings were constructed on the Waegebrughe campus: west and east of the church.

CLIENT

VZW the Vijvens

DESIGNER / ARCHITECT

sergison Baetes architects

LOCATION

Kruisem

BUDGET TECHNIQUES

approx. EUR 6,710,761

SURFACE

12.000m2

PERIOD STUDY

09/2013 - 12/2018

Period EXPERIENCE

05/2019 - 05/2022

WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem

WZC Waegebrughe Kruisem

The non-profit organization Vijvens provided a new residential care center in Kruisem on the Marolle: Waegebrughe. Two buildings were constructed on the Waegebrughe campus: west and east of the church.

A total of sixty rest home beds, twenty service flats, thirty assisted living or care flats, a day care center with fifteen places, nine short-stay rooms, two night care rooms and a center for the young demented, administrative and communal functions, large kitchen, technical and other facility rooms were created.

The large-scale project further includes a local service center with a social restaurant, a wellness for the elderly and a daycare center. This will provide a link to the neighborhood and associations.

Ingenium was responsible for the integral study of the techniques: sustainability studies, EPB reporting.

Study, design, competition file, follow-up of the works, commissioning on delivery, budget control, for these techniques: elevators, HVAC, kitchen, plumbing, elevators, electricity.

In terms of sustainability, the following interventions toward reusable energy are planned:

  • BEO field with passive cooling and heat pump for heating
  • Charging points for electric vehicles
  • For the residential units : storey stations with separate heat exchangers and energy metering
  • Cogeneration (does consume gas...)

Flexibility in design was provided in this way:

  • For each building, substations are provided for the techniques
  • A large number of technical ducts are provided per building so that extensions can easily be added
  • The distribution of techniques in the building is centralized by a horizontal distribution in the basement that then rises vertically to the floors through the ducts.

WZC Waegebrughe Kruisem
Oops! Something went wrong while submitting the form.

WZC Waegebrughe Kruisem

The non-profit organization Vijvens provided a new residential care center in Kruisem on the Marolle: Waegebrughe. Two buildings were constructed on the Waegebrughe campus: west and east of the church.

CLIENT

VZW the Vijvens

DESIGNER / ARCHITECT

sergison Baetes architects

LOCATION

Kruisem

BUDGET TECHNIQUES

approx. EUR 6,710,761

SURFACE

12.000m2

PERIOD STUDY

09/2013 - 12/2018

Period EXPERIENCE

05/2019 - 05/2022

WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem
WZC Waegebrughe Kruisem

WZC Waegebrughe Kruisem

The non-profit organization Vijvens provided a new residential care center in Kruisem on the Marolle: Waegebrughe. Two buildings were constructed on the Waegebrughe campus: west and east of the church.

A total of sixty rest home beds, twenty service flats, thirty assisted living or care flats, a day care center with fifteen places, nine short-stay rooms, two night care rooms and a center for the young demented, administrative and communal functions, large kitchen, technical and other facility rooms were created.

The large-scale project further includes a local service center with a social restaurant, a wellness for the elderly and a daycare center. This will provide a link to the neighborhood and associations.

Ingenium was responsible for the integral study of the techniques: sustainability studies, EPB reporting.

Study, design, competition file, follow-up of the works, commissioning on delivery, budget control, for these techniques: elevators, HVAC, kitchen, plumbing, elevators, electricity.

In terms of sustainability, the following interventions toward reusable energy are planned:

  • BEO field with passive cooling and heat pump for heating
  • Charging points for electric vehicles
  • For the residential units : storey stations with separate heat exchangers and energy metering
  • Cogeneration (does consume gas...)

Flexibility in design was provided in this way:

  • For each building, substations are provided for the techniques
  • A large number of technical ducts are provided per building so that extensions can easily be added
  • The distribution of techniques in the building is centralized by a horizontal distribution in the basement that then rises vertically to the floors through the ducts.

WZC Waegebrughe Kruisem

Related projects

Green Energy Park

Green Energy Park
In the spotlight

Master plan Energy UZ Gasthuisberg Leuven

Master plan Energy UZ Gasthuisberg Leuven
In the spotlight

Renovation of cooling plant lab building Zwijnaarde

Renovation of cooling plant lab building Zwijnaarde
In the spotlight

Framework contract UZ Brussel

Framework contract UZ Brussel
In the spotlight

Project ACCESS: Parking Keerdok City of Mechelen

Project ACCESS: Parking Keerdok City of Mechelen
In the spotlight

Rezoning monastery visitation Kraainem

Rezoning monastery visitation Kraainem
In the spotlight

AZ Sint-Jan: Mortuary renovation

AZ Sint-Jan: Mortuary renovation
In the spotlight

AZ Sint-Jan: Renovation orthopedics

AZ Sint-Jan: Renovation orthopedics
In the spotlight

AZ Sint-Jan: Renovation lab

AZ Sint-Jan: Renovation lab
In the spotlight

UZ Gasthuisberg Leuven - Power station O&N4

UZ Gasthuisberg Leuven - Power station O&N4
In the spotlight

UZ Brussel Laboratory of genetics

UZ Brussel Laboratory of genetics
In the spotlight

NN Group Brussels data center

NN Group Brussels data center
In the spotlight

Also bitten by
smart technology?